Industrial/process
Select A Project:
AmerenUE Meramec Power Plant, Boeing Track II,
Holcim, Chrysler, Pfizer
Pfizer Global Research & Development
CV SUMP Generator & Power Distribution | Chesterfield, MO
Like replacing a car engine while it was running - the electrical upgrade at Pfizer's Chesterfield campus was so complex that two pre-qualified electrical contractors declined to bid the work. PayneCrest accepted the challenge and more than doubled the power capabilities of the campus to support - without disrupting - Pfizer's expansion of its pilot production of biologic drugs for clinical trials. Its work included:
- Avoiding a campus-wide shutdown by limiting planned building outages to four hours or less. PayneCrest deftly managed all outages, which were scheduled six months ahead of time.
- Employing value engineering techniques and creative use of manpower to adhere to budget guidelines and save Pfizer $350,000.
- Meeting all schedule milestones even as six months were being shaved from the originally envisioned 16-month schedule.
- Creatively consolidating three assignments and integrating multiple engineering teams for greater efficiency.
- Adapting to potential delays when its generator supplier was forced to redirect generators originally destined for the Pfizer project to the U.S. Department of Defense.
- Instituting intensive high voltage safety training and other risk management protocols. PayneCrest logged more than 11,000 man hours without a recordable injury.
PayneCrest also diligently worked with two Pfizer consultants hired to oversee stringent design and installation requirements endemic to the pharmaceutical industry. In the end the 10-month long project was completed on time, within budget and without a single unplanned outage.
|